At Oran Park, we keep you up to date with your lot’s registration.

Once these works have been completed and gone through council approval, the land is then registered at the NSW Land Registry Services.

After registration, settlement on the land is approved – this process generally takes around 21 days. Once finalised, you’re welcome to choose your preferred builder and prepare house plans to submit for Oran Park assessment.

Release Number Lot Numbers Expected Construction Completion Expected Council Approval of Plan Expected Registration by Land Registry Services Anticipated Settlement
41/2 (Brabham Precinct) Lots 2001 – 2120
Lots 2201 – 2269
Completed
Dec 2024
Approved
Jan 2025
Jan 2025
Jan 2025
Jan 2025
Feb 2025
41-3 All lots May 2025 June 2025 July 2025 August 2025
28-2 All lots May 2025 June 2025 July 2025 August 2025

The above times are our best estimates of likely dates based on the information available at the date of publication. These dates are subject to change without notice as many issues are beyond the control of Oran Park.

Oran Park accepts no liability as a result of any delays to these timeframes.

Information correct as at 29th November 2024.